SynchroGrid performed engineering calculations to verify that relay settings complied with PRC-025-2 for four Cottonwood generation units. The purpose of this standard is to prevent unnecessary tripping of generators and equipment damage by correctly setting load-responsive relays.

SynchroGrid’s responsibilities included reviewing relay one-line/three-line diagrams and applicable relay settings, performing calculations to verify relay settings complied with PRC-025, suggesting settings changes for non-compliant relays, and producing compliance reports.

Interested in expanding your system protection capabilities? Let’s talk about your challenges and ways we can help to provide unparalleled system protection services. Give us a call.