The time overcurrent and zone settings per PRC-025-1 application guidelines were investigated in detail to evaluate if they comply. 

SynchroGrid performed engineering calculations to verify that relay settings are in compliance with PRC-025-1 for all wind farms located within the United States.

Similar projects

BTU: NERC PRC-019-2

SynchroGrid conducted a coordination review utilizing compliance of NERC PRC-019-2 at Roland C. Dansby Power Plant.

Pattern Energy: PRC-025-1 Compliance

SynchroGrid performed engineering calculations to verify that relay settings are in compliance with PRC-025-1 for Pattern Energy wind farms located in the US.

Sharyland Utilities: NERC PRC-019-2 Compliance for Alibates Synchronous Condenser

SynchroGrid performed engineering calculations for Sharyland Utilities to verify that the relay and limiter settings at the Alibates Substation were in compliance with NERC PRC-019-2.

Sharyland Utilities: NERC PRC-019-2 Compliance for Tule Canyon Synchronous Condenser

SynchroGrid performed engineering calculations for Sharyland Utilities’ Tule Canyon Substation to verify that relay and limiter settings were in compliance with NERC PRC-019-2.

CTT: NERC PRC-002-2 Compliance

SynchroGrid reviewed substation settings to ensure compliance with NERC PRC-002-2 for Cross Texas Transmission.

Pattern: NERC PRC-024-2 Compliance

SynchroGrid reviewed the protection relay settings for Pattern Energy's Panhandle substation. 

Pattern: NERC PRC-019-2 Compliance

SynchroGrid performed engineering calculations to verify that relay settings were in compliance with NERC PRC-019-2 for all wind farms located in the United States.

ACCIONA: NERC PRC-025-1 Compliance

SynchroGrid implemented NERC PRC-025-1 Generator Relay Loadability to assess load response settings. 

BTU: NERC PRC-005-6

SynchroGrid created standard relay maintenance procedures and documentation to ensure compliance with NERC PRC-005-6 for Bryan Texas Utilities. 

BTU: NERC PRC-024-2 Review

SynchroGrid reviewed the protection relay settings for Bryan Texas Utilities to ensure compliance with PRC-024-2.

NRG: Generator NERC-PRC-025-1 Compliance Review

SynchroGrid created an innovative process that has simplified the verification of generator protective relays for NERC PRC-025 compliance. 

Pattern: Wind Farm System Protection Compliance Review

SynchroGrid performed extensive calculations for wind farms across Canada to ensure that their relay settings were in compliance with a number of NERC-PRC standards.