SynchroGrid provided substation design services to install a second transformer.

The services included:

  • Generation of design drawings to accomodate a new transformer
  • Generation of system protection drawings and schematics
  • Review of manufacture drawings
  • Creation of relay settings for SEL-501 and SEL-587E
  • Relay coordination between transformer and feeders

Similar projects

Garland Power & Light: 138kV Transformer Upgrade

SynchroGrid provided services for Garland Power and Light to upgrade a 138kV transformer.

CTT: 345kV Reactor Inrush DFR Solution

SynchroGrid developed a DFR solution to monitor reactor inrush currents. This will enable CTT to build a database of waveform signals to analyze and detect abnormal conditions.